NONFERROUS METALLIC MINERAL MINING

House Bill 6243

Sponsor:  Rep. Tom Casperson

Committee:  Agriculture and Resource Management

Complete to 11-8-04

A SUMMARY OF HOUSE BILL 6243 AS INTRODUCED 9-29-04

The bill would create a new Part 632 of the Natural Resources and Environmental Protection Act relating to the mining of nonferrous metallic minerals (i.e., where iron is not the predominant metal extracted).

Permit Application

The bill would prohibit a person from mining nonferrous metallic minerals except as authorized by a permit issued by the Department of Environmental Quality (DEQ).  The permit application would have to include the following: (1) a $5,000 application fee; (2) an environmental impact assessment; (3) a mining, reclamation, and environmental protection plan that seeks to minimize the adverse impacts of the mining operation on natural resources, the environment, and public health; (4) a contingency plan that includes an assessment of the environmental, public health, and safety risks that may result from failures of the mining operation, and the operator's notification and response plans; and (5) financial assurances of the mining operation. 

The bill also provides that the applicant would have the burden of establishing that the terms and conditions provided in the application, environmental protection plan, and environmental impact assessment results in a mining operation that reasonably minimizes the actual or potential adverse impacts on air, water, and other natural resources. 

Permit Review Process

After receiving an application, the DEQ would have 14 days to determine whether the application is administratively complete – that is, it contains all of the required information and fees.  If the application is not complete, the DEQ would have to notify the applicant of the deficiency.  If the DEQ does not make a determination as to whether the application is "administratively complete", the application would automatically be considered as such.  The DEQ would have to provide a public hearing on an application within 42 days after it is considered to be administratively complete. The DEQ would have to provide appropriate public notice of the hearing, and would accept written public comments on the application for 28 days after the public hearing. 

The DEQ would be required to make a preliminary decision to grant or deny the application within 28 days after the close of the public comment period.  Once that preliminary decision is made, the DEQ would be required to hold another public hearing (with appropriate notice) on that preliminary decision, and also accept written public comment for 28 days after the public hearing. 

Permit Approval

The DEQ would be required to make a decision to approve or deny the application within 28 days after the close of the public comment period on its preliminary decision.  The DEQ could require additional information from the applicant to make its decision.  The 28-day period would then be tolled until the DEQ receives the additional information.  

The DEQ would be required to approve the application if it determines that the application meets the requirements set forth in Part 632 and the proposed mining operation will not pollute, impair, or destroy the air, water, or other natural resources or the public trust in those resources in accordance with Part 17 of the act. The excavation and removal of nonferrous metallic mineral and associated rocks and materials would not, in and of itself, constitute pollution, impairment, or destruction of those natural resources.  The DEQ would have to deny the application if the above requirements are not met. 

Once the permit is approved, the terms and conditions provided for in the application and the mining, reclamation, and environmental protection plan would become part of the mining permit. 

The bill also provides that if a person submits an application for a mining permit and other permits required under the NREPA, that DEQ could process those applications in a coordinated manner (as appropriate) to facilitate the timely review of the applications, including holding one public hearing for multiple permit applications. 

Permit Effectiveness

A mining permit issued by the DEQ would remain in effect until it is terminated or revoked by the DEQ.  The DEQ could terminate a permit if (1) the permit holder has not begun constructing the plant facilities or has not conducted actual mining activities within two years after the effective date of the permit, or (2) if the permit holder has completed reclamation of the mining area and requests that the permit be terminated, and the natural resources around the mining operation are not polluted, the permit holder has fulfilled the requirements of the DEQ to protect the environment, and the requirements of the post-closure monitor period have been satisfied.  The DEQ could revoke a mining permit if the operator has violated Part 632, a related rule, or a provision of the permit. 

A permit could be transferred to a new operator with approval of the DEQ and public notice.  The person acquiring the permit would have to provide the DEQ with financial assurances and accept the conditions provided in the existing permit.   If the current permit holder is in violation of the act, related rules, or the permit, the permit would not be transferred until the permit holder has taken the necessary corrective actions or the person acquiring the permit has entered a written consent agreement with the DEQ to correct the violations. 

Amendments to the Permit

The provisions of a permit could be amended to address anticipated changes in the mining operation or if the DEQ determines that the permit does not reasonably protect the environment, natural resources, or public health and safety.  If the DEQ determines that the amendment is significant, the amendment could be subject to the same review process for new permit applications.  If the amendment is not significant, the DEQ would have to provide written notice to local municipalities and tribal governments, provide notice in a local newspaper, and approve the amendment 14 days after the public notice. 

Permit Holder Responsibilities

If mining operations are suspended for at least 90 days, the permit holder would have to maintain the mining area and conduct any interim sloping or surface stabilization necessary to protect the environment, natural resources, or public health and safety. 

Reclamation activities would have to be conducted in accordance with the approved mining, reclamation, and environmental protection plan.  Final reclamation would have to begin within three years after the mining operations cease, and would have to be completed by the time provided in the mining, reclamation, and environmental protection plan.  However, the required start and completion dates could be extended with the approval of the DEQ. 

A permit holder would be required to conduct groundwater and surface water monitoring during the mining operations and the 20-year post-closure monitoring period.  The permit holder would have to notify the DEQ at least 18 months prior to the proposed ending date of the post-closure monitoring period, and provide the DEQ with information demonstrating the basis for ending the monitoring period. 

The post-closure monitoring period could be lengthened or shortened by the DEQ.  The monitoring period would be extended (in increments of up to 20 years) unless the DEQ determines at least one year prior to the end of the monitoring period that there is no significant potential for water contamination resulting from the mining operation.  The DEQ could shorten the monitoring period at any time if it determines that there is no significant potential or water contamination resulting from the mining operation.  However, the monitoring period would only be lengthened or shortened after a public hearing on the matter. 

In addition, both the mining area and the area affected by the mine would have to be reclaimed and remediated to achieve a self-sustaining ecosystem that does not require perpetual care after the mine closes, and with the goal that the ecosystem of the affected area be restored to the conditions that existed prior to mining.  However, any portion of the mining area that is owned by the permit holder could be used for any legal purpose. 

Financial Requirements

An operator would have to maintain financial assurance for all mining and reclamation operations until the DEQ determines that all reclamation has been completed and through the post-closure monitoring period.  The financial assurance would include a conformance bond, escrow, cash, certificate of deposit, irrevocable letter of credit, or equivalent security (or any combination thereof) covering at least three-quarters of the total amount required.  The financial assurance for the remaining balance would consist of a statement of financial responsibility.  The statement of financial responsibility and the financial assurance would be adjusted (as necessary) every three years or as often as the DEQ considers necessary.  Failure to provide adequate financial assurance would be grounds for the immediate suspension of mining operations. 

Report to the DEQ

A permit holder would be required to file a mining and reclamation report to the DEQ on or prior to March 15.  The report would include a status of the mining and reclamation operations, an update of the contingency plan, monitoring results, and a description of the material mined from the mining area.  In addition, a permit holder would be required to promptly notify the DEQ of any incident, act of nature, or activity that exceeds permit standards that has created or may create a threat to the environment, natural resources, or public health or safety.  (Such information would also have to be provided in the annual report.) 

Nonferrous Metallic Mineral Surveillance Fee

The bill would assess a permit holder a fee not exceeding five cents per ton of material mined from the mining area, but not less than $5,000 total, for each calendar year the mine is in operation and during the post-closure monitoring period.  The actual rate of the fee would be the ratio (to the nearest 1/100 of one percent) of the amount appropriated in the current fiscal year for surveillance, monitoring, administration, and enforcement of Part 632 to the total tons of material mined.  The fee would be due within 30 days after the permit holder receives notice from the DEQ of the amount due.  If the fee is not paid on time, a penalty equal to 10 percent of the amount due or $1,000 (whichever is greater) would be assessed against the permit holder. 

Nonferrous Metallic Mineral Surveillance Fund

The fee would be deposited into a newly created nonferrous metallic mineral surveillance fund.  Money in the fund would only be expended, upon appropriation, for surveillance, monitoring, administration, and enforcement pursuant to Part 632. 

Contested Hearings

A person who is aggrieved by an action of the DEQ could file a petition with the DEQ requesting a contested case hearing under the Administrative Procedures Act.  A petition filed more than 60 days after the action could be rejected as being untimely.  The DEQ would have to provide notice of the hearing to local municipalities and federally recognized Native-American tribes, and also provide notice in a local newspaper. 

Violations

If the DEQ determines that an operator has violated Part 632, related rules, or a provision of the mining permit, the DEQ would require the operator to correct the violation.  If the violation results in imminent and substantial danger to the public health or safety, environment, or natural resources, the DEQ could revoke the mining permit, suspend the activities at the mining operation, or order the operator to eliminate the danger.  Before the DEQ suspends the activities at the mining operation or revokes the mining permit, the DEQ would have to notify the operator in writing and provide an evidentiary hearing.  However, if the DEQ determines that emergency action is necessary, it may issue an emergency order lasting no more than 21 days. 

If the operator or surety fails to correct a violation or take corrective action, the DEQ could enter the mining area and take whatever action is necessary to remediate any damage to the environment and public health resulting from the violation.  The operator or surety would be jointly and severally liable for any expenses incurred by the DEQ, and would be required to pay such expenses within 30 days.  The DEQ could bring a lawsuit for the collection of those expenses. 

The bill also specifies that the revocation of a mining permit or the suspension of activities at a mining operation would not relieve the permit holder of its responsibility to complete reclamation, maintain financial assurance, and undertake appropriate measures to protect the environment, natural resources, and public health and safety. 

If the DEQ receives an allegation and evidence of a violation of Part 632, related rules, or a provision of the permit, the DEQ would have to record the allegation and conduct an inspection of the mining operation within five business days after receiving the allegation.  The DEQ would have to provide a written report to the operator and person making the allegation within 15 days after the investigation has been completed. 

Civil Action

The DEQ could request the attorney general to commence a civil action for appropriate relief for a violation of Part 632, related rules, a provision of the permit, or departmental order in the Ingham County Circuit Court, or the circuit court of the county where the defendant is located, resides, or is doing business.  The court would have the authority to restrain the violation and require compliance, and could impose a civil fine of at least $2,500 and award reasonable attorney's fees and costs.  However, fine could not exceed $25,000 per day of violation.  If the court finds that the violation substantially endangers the public health, safety, or welfare, the court would impose a fine between $500,000 and $5 million. 

In addition, the attorney general could file a civil suit to recover the full value of the injuries done to the natural resources of the state and the costs of surveillance and enforcement of Part 632. 

A person who makes a false representation in a permit application or report to the DEQ would be guilty of a felony and could be imprisoned for not more than two years and would be fined between $2,500 and $25,000 for each violation.  Second and subsequent convictions be would subject to a fine between $25,000 and $50,000 per day. 

In addition, the if the court determines that the criminal defendant posed a substantial threat to the public health, safety, or welfare, the court would impose, in addition to other penalties, a prison sentence of five years and a fine of $1 million.

A defendant would be criminally or civilly liable if it is determined that he or she knowingly or recklessly acted in such a manner that resulted in a potential for death or serious bodily injury and (1) had awareness that the conduct would cause a substantial danger of death or serious bodily harm, or (2) acted in gross disregard of the standard of care that any reasonable person should observe in a similar situation. 

                                                                                           Legislative Analyst:   Mark Wolf

                                                                                                                       

This analysis was prepared by nonpartisan House staff for use by House members in their deliberations, and does not constitute an official statement of legislative intent.